- Design and Engineering
- August 2000 to March 2001
|
|
|
ConstructionApril 2001 to November 2002
|
|
| CONSTRUCTION MILESTONE DATES
|
| Site MobilizationApril 2, 2001
|
| Erect Tower CraneMay 15, 2001
|
| Temporary Partitions/4th FloorMay 29, 2001
|
| Start Dome Steel ErectionJune 20, 2001
|
| Complete Dome Steel ErectionJanuary 2002
|
| Complete Exterior DomeJune 2002
|
| Start Dome Interior FinishesMay 2002
|
| Erect Exterior StatueOctober 2002
|
| Complete Dome Interior FinishesNovember 2002
|
| Dedication of DomeNovember 16, 2002