|
|
|
October 1, 2001
The second level of steel is installed.
|
|
|
|
October 9, 2001
The first section of the dome steel is being raised.
|
|
|
|
October 9, 2001
Dome steel sections are tied into the compression ring.
|
|
|
|
October 9, 2001
The circular opening where the spiral stairs rise inside the dome.
|
|
|
|
October 10, 2001
Concrete is poured at the buttress level.
|
|
|
|
October 12, 2001
Ironworkers tie on top the dome steel.
|
|
|
|
October 12, 2001
Dome steel is lifted into place.
|
|
|
|
October 12, 2001
Ironworker installs the dome steel.
|
|
|
|
October 17, 2001
Aerial view of the complete dome steel taken from the tower crane.
|
|
|
|
October 18, 2001
Front steps view of the completed dome steel.
|
|
|
|
October 19, 2001
Concrete is poured at the buttress level.
|
October 19, 2001
Below: the Oklahoma City skyline viewed through the dome steel. |
|
|
|
|
|
|
October 25, 2001
Dome steel rises
above the weather
protective box.
|
|
|
|
October 26, 2001
Pediment window
enclosures prepped for
installation.
|
|
|
|
October 30, 2001
Mechanical mezzanine
steel reaches toward the
oculus.
|
|
|
|
October 30, 2001
Steel dome frame of
the Oklahoma City State
Capitol.
|